
All proposals must be coordinated by OSP and routed through Cayuse SP. This also applies to preliminary proposals or pre-applications if it:
- Must be submitted by the Office of Sponsored Programs,
- Requires an Authorized Official intuitional signature,
- Has a line item budget, or
- Includes matching.
Cayuse to HGA Transition Plan
Overview
The UT System is transitioning from the Cayuse platform to the DASH Research – Huron Grants & Agreements (HGA) module for sponsored projects. While the transition will temporarily disrupt normal business operations, OSP and SPA have developed a plan to make the transition as smooth as possible. Key elements include:
- Data Import: At HGA go-live, the only data imported into the new HGA system will be fully processed active awards, migrated from the DASH – Project Portfolio Management (PPM) module. A “stub” proposal record will be created using data from DASH PPM. Cayuse records will not be imported due to irreconcilable technical mismatches between the systems (i.e., Cayuse vs. DASH); however, Cayuse data will remain accessible through a data repository. As awards are received for currently pending proposals, OSP and SPA will re-enter those proposals into HGA as part of the award setup process, creating a complete record in DASH Research – HGA.
- Transition & “Dark Period”: To prepare for the transition and award import, OSP and SPA will pause data entry ahead of the transition to ensure no records are lost. In addition, there will be a production cutover period, or “Dark Period” production cutover period between Cayuse going dark and the DASH Research – HGA going live. The timeline below outlines a detailed continuity plan to support operations throughout the production cutover period.
- DASH PPM Dark Period (November 25 – December 7) – DASH PPM will be unavailable for the following activities between November 25 and December 7:
- Creation of new Awards or SPNs
- Modification of Award or SPN elements
- Expenses, including labor distributions and cost transfers, can still be processed.
- Cayuse Dark Period (December 4 – December 7) – There will be no routing or record system available. Cayuse will go-dark on December 4 and HGA will not go-live until December 7. During this time, proposals cannot be electronically routed or approved. Awards cannot be recorded.
- DASH PPM Dark Period (November 25 – December 7) – DASH PPM will be unavailable for the following activities between November 25 and December 7:
- Questions? Contact aggrant@utk.edu.
CLICK HERE FOR THE FULL, DETAILED TRANSITION PLAN, INCLUDING TEMPORARY MINIMUM LEAD TIMES
Standard Proposal Guidance
To notify OSP of an upcoming proposal, complete our online Proposal Intake Questionnaire, as soon as you start planning, to provide preliminary information about your prospective proposal. This information does not have to be final at this time; it will be used by the assigned OSP Coordinator to provide detailed guidance for development, routing, and submission of your proposal.
A grant coordinator will be assigned to work with you, help develop your budget, and shepherd the proposal through to submittal in Cayuse SP and to the agency. The coordinator will review the RFA in detail and help establish a timeline so the proposal package is fully complete and ready for submission. This will allow ample time for review and dealing with any problems.
Your OSP Coordinator will help prepare your proposal budget, and your departmental business manager can answer questions related to budget items (estimated cost, GL codes in IRIS, etc.) See UTIA Indirect Cost Guide for help determining activity classification and indirect cost rates.
If you are not contacted by a coordinator within two days of completing the questionnaire, please email aggrant@utk.edu to ensure a coordinator has been assigned.
Even if a proposal or contract will be submitted directly by a faculty or staff member, prior approval of the UTIA Sponsored Programs office is required. This is to protect you as an employee and the institution.
UTIA Office of Sponsored Programs (OSP)
minimum lead times for proposal notification to OSP
OSP strives to ensure excellent support and successful submittal of a thoroughly reviewed proposal by sponsor deadline or target submittal date. As soon as you know of your intention or begin planning to submit an upcoming proposal, immediately notify OSP (e-mail aggrant@utk.edu). To ensure a smooth and successful submission, the following minimum lead times (MLTs) are required to notify OSP of a proposal that has certain components/characteristics.
| MLT | Proposal components/Characteristics |
| 3 months: | 4 or more subawards; international collaborations; review by Orange Team, Hanover, or UTK Research Development Team |
| 8 weeks: | 1-3 subawards |
| 4 weeks: | Federal sponsor; co-PIs from other UT campuses; cost share requirement; special approvals such as voluntary F&A reduction |
| 3 weeks: | Budget with multiple UTIA departments and /or F&A rates; includes a REC |
| 2 weeks: | One department; no subawards; no cost share; no personnel from other campuses; no special approvals; non-federal sponsor |
These MLT-s apply whether UTIA is the lead institution on the proposal, or a subaward/ collaborating UT campus. If UTIA is a subaward or a collaborating campus, the MLT-s are based on the day the lead applicant needs materials, which is typically at least a week before the sponsor deadline.
Once notified, the coordinator will provide additional internal deadlines that must be met. OSP will submit a monthly report to the respective department head and associate deans of proposals for which the MLTs of notification and additional internal deadlines were not met.
Additional considerations:
- The level of support given to proposals that fail to meet the MLTs of notification or internal deadlines will depend on the workload of the coordinator.
- The coordinator will make every effort to assist in successful development and submittal, but proposals that adhere to internal timelines will take priority.
- When internal deadlines are not met, the PI is responsible for any failure of the proposal to be submitted by the deadline, for the proposal being returned without review by the sponsor, or for any delays in award setup stemming from the proposal not being submitted by OSP or being submitted with limited or no OSP review.
- If PIs cannot meet the MLTs of notification due to circumstances beyond their control, such as the RFA was just issued, explanation should be included with the notification.
- Proposals for which notification to OSP is received less than 5 full business days before the sponsor submittal deadline will not be assigned to a coordinator or submitted by OSP unless department head and dean’s office approval is received. If approval is obtained, the proposal will be submitted with limited to no review.
UTIA faculty may supplement their UT salary through the UTIA Salary Incentive Plan (SIP). If interested in getting SIP for a project, the PI should let the OSP coordinator know at the time of the proposal. Applications will be processed at the time of the award. SIP applications can be found on the Forms page.
See Standard UTIA Info.
Our objectives are to assist faculty in the proposal preparation and submission process and to increase our competitiveness in securing extramural funding. If you have questions or concerns, please feel free to contact us.